Commissioned asset
Low priority27
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
4 registered wind units commissioned in Barver, Niedersachsen — 17.04 MW combined
Barver, Niedersachsen
Asset typeHorizontalläufer
Energy carrierWind
Registered operatorLandvolk-Dienstleistungsgesellschaft Grafschaft Diepholz mbH
Commercial interpretation
The registered asset moved from a planned MaStR operating status to a non-planned status.
Change summary
- Combined registered capacity across grouped units
- 17.04 MW
- Registered units
- 4
- Asset type
- Horizontalläufer
- Energy carrier
- Wind
- Location
- Barver, Niedersachsen
- Registered operator
- Landvolk-Dienstleistungsgesellschaft Grafschaft Diepholz mbH
- Operating status
- In Betrieb
- Lifecycle change
- Planned → commissioned
- Commissioning date
- 2026-09-04
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (4)
SEE993780521998View official MaStR record ↗SEE998947234865View official MaStR record ↗SEE917769117538View official MaStR record ↗SEE910750172622View official MaStR record ↗
Grouping basis
Grouping basisSame site, operator, technology and change type
These are separate MaStR registrations at the same site that share a registered operator, technology and the same kind of registry change in the same registry update. GridGraph groups them for presentation only and does not assert that this grouping represents one canonical development project.
These are separate MaStR registrations at the same site that share a registered operator, technology and the same kind of registry change in the same registry update. GridGraph groups them for presentation only and does not assert that this grouping represents one canonical development project.
Snapshot transition
22 Sept 2026 → 23 Sept 2026