Opportunity · High73
The opportunity score estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Opportunity score 73
- Project scale (MW): 16
- Event type: 14
- Lifecycle stage: 10
- Recency: 8
- Operator identified: 10
- Multi-unit evidence: 6
- Several changes together: 5
- Size of change: 4
Signal materiality 63
- Event type: 18
- Size of change: 17
- MW affected: 12
- Units affected: 10
- Several changes together: 6
Multiple registry changes (capacity + schedule) — 4 units / 24.88 MW
Stadtlohn, Nordrhein-Westfalen · Operator: Windenergie Almsicker Feld GmbH & Co.KG
4 units · 24.88 MW
What changed
4 wind units registered a capacity change; combined registered capacity moved from 28.8 MW to 24.88 MW (-3.92 MW). 4 wind units registered a later planned commissioning date (+151 days).
Why this ranks high. Mid-sized 24.88 MW signal, 4 registrations moving together, capacity and schedule changes recorded together on the same units and the registered operator is known.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Grid-connection / interconnection and electrical infrastructure services
- Engineering and environmental services
Verify next
- Check whether the change reflects a design or turbine-model change
- Verify whether the date change reflects real rescheduling or a registry correction
- Compare with permit and grid-connection documents
- Check permitting and construction status
- Look for recent developer announcements
- Look for recent developer updates
Change summary
- Per-unit change
- 4 units changed from 7.2 MW to 6.22 MW each
- Combined registered capacity now
- 24.88 MW
- Combined change
- -3.92 MW (-14%)
- Units with a new planned date
- 4
- Planned commissioning (same for every unit)
- Jan 2027 → Jun 2027 (+151 days)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (4)
SEE944587508781View official MaStR record ↗SEE930547865124View official MaStR record ↗SEE941027955228View official MaStR record ↗SEE927161512879View official MaStR record ↗
Grouping basis
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
23 Sept 2026 → 24 Sept 2026