Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 5 registered wind units in Wanderup, Schleswig-Holstein

Wanderup, Schleswig-Holstein

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorWindpark Kieracker UG (haftungsbeschränkt) & Co. KG
A later registered planned commissioning date may indicate asset delay or rescheduling.
Registered units
5
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Wanderup, Schleswig-Holstein
Registered operator
Windpark Kieracker UG (haftungsbeschränkt) & Co. KG
Operating status
In Planung
Planned commissioning
Sept 2027 → Dec 2028
Change
+484 days

These units also registered the change(s) below in this same update. They are shown for completeness and do not change the primary signal above.

Capacity change
Registered capacity
4.8 MW → 7 MW (+2.2 MW / 46%)

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisConservative municipality/operator/category grouping
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.

1 Jul 2026 → 11 Sept 2026