Weekly intelligence brief

German Energy Asset Change Intelligence — 2026-09-13

A curated, source-traceable view of registered MaStR asset updates. MaStR records individual registered units. GridGraph groups closely related units in this brief for presentation only; these groups are not asserted to be canonical development projects.

1,988 registry changes detected → 45 commercially relevant groups selected

1,988Registry changes detected
Every field-level change GridGraph found between the previous and current MaStR snapshot — not yet filtered for commercial relevance.
1,908Unique registrations affected
Each MaStR registration is counted once even if it triggered more than one change. Combined registered capacity across these registrations: 27.23 GW.
749Candidate groups formed
Changes are grouped by registration, site and change type before curation. Not every candidate group is commercially significant enough to include below.
45Curated groups shown
The highest-scoring candidate groups, capped per category, selected for this brief. See the priority score on each card for why a group was included.

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.

Relevant Bundesländer (optional)
Relevant technologies (optional)

We'll only use this to follow up with a filtered weekly brief for your market. Read how your data is stored and how to withdraw at any time in our Privacy Policy.

Top changes to watch (12)

Composite change
Critical priority93

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Major asset update in Neukieritzsch, Sachsen

Gasturbinen mit Abhitzekessel

Registered capacity
875 MW → 391.17 MW (-483.83 MW / -55%)
Registered operator
Lausitz Energie Kraftwerke AG → Gaskraftwerk Lippendorf GmbH

Multiple material registration changes occurred in the same source transition and may warrant investigation.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE973821807274

Composite change
Critical priority93

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Major asset update in Spreetal, Sachsen

Gasturbinen mit Abhitzekessel

Commissioning
Sept 2029 → Oct 2031 (+761 days)
Registered capacity
870 MW → 391.17 MW (-478.83 MW / -55%)
Registered operator
Lausitz Energie Kraftwerke AG → Gaskraftwerk Schwarze Pumpe GmbH

Multiple material registration changes occurred in the same source transition and may warrant investigation.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE960894923635

Capacity change
Low priority41

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered capacity changed for Horizontalläufer in Steinreich, Brandenburg

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Steinreich, Brandenburg
Registered operator
Alterric Deutschland GmbH
Operating status
In Planung
Registered capacity
4.2 MW → 7.2 MW
Change
+3 MW

A material capacity increase indicates a larger registered asset capacity than in the previous snapshot.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE994076161874

Composite change
Low priority41

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Major asset update in Großenwiehe, Schleswig-Holstein

Horizontalläufer

Commissioning
Sept 2027 → Dec 2028 (+484 days)
Registered capacity
4.8 MW → 7 MW (+2.2 MW / 46%)

Multiple material registration changes occurred in the same source transition and may warrant investigation.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE998320722927

Timing change
High priority76

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delay for 60 MW Gasturbinen mit Abhitzekessel in Frankfurt am Main, Hessen

Gasturbinen mit Abhitzekessel

Combined registered capacity across grouped units
124.04 MW
Registered units
3
Asset type
Gasturbinen mit Abhitzekessel
Energy carrier
Erdgas
Location
Frankfurt am Main, Hessen
Registered operator
Mainova AG
Operating status
In Planung
Planned commissioning
Sept 2026 → Nov 2026
Change
+64 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 3 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE918810715130, SEE900931819460, SEE975123428881

Timing change
High priority75

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delay for 15 MW Horizontalläufer in Ausschließliche Wirtschaftszone

Horizontalläufer

Combined registered capacity across grouped units
180 MW
Registered units
12
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Ausschließliche Wirtschaftszone
Registered operator
EnBW He Dreiht GmbH & Co. KG
Operating status
In Planung
Planned commissioning
Jun 2026 → Oct 2026
Change
+93 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 12 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE959171440316, SEE983599520046, SEE923954894696, SEE998812552131, SEE980282368237, SEE926317316675, SEE918479491512, SEE980292520984, SEE951024907250, SEE977091784846, SEE956282536914, SEE908981182558

Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delay for 6.8 MW Horizontalläufer in Namborn, Saarland

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Namborn, Saarland
Registered operator
KS Energiesysteme GmbH & Co. KG
Operating status
In Planung
Planned commissioning
Jan 2026 → Sept 2029
Change
+1368 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE961749418528

Operator change
Low priority35

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered operator changed for Horizontalläufer in Alsheim, Rheinland-Pfalz

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Alsheim, Rheinland-Pfalz
Operating status
In Planung
Registered operator
ABO Energy Windpark 23 GmbH & Co. KG → Vattenfall Wind Mettenheim GmbH

A registered operator change may warrant investigation of the registered asset's current commercial context.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE969716045593

Operator change
Low priority35

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered operator changed for Horizontalläufer in Balve, Nordrhein-Westfalen

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Balve, Nordrhein-Westfalen
Operating status
In Planung
Registered operator
PNE AG → Windpark Balver Wald Betriebs GmbH & Co. KG

A registered operator change may warrant investigation of the registered asset's current commercial context.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE986579804563

New planned asset
Critical priority100

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

New planned 880.4 MW Gasturbinen mit nachgeschalteter Dampfturbine in Voerde (Niederrhein), Nordrhein-Westfalen

Gasturbinen mit nachgeschalteter Dampfturbine

First observed
2026-09-11
Registered capacity
880.4 MW
Asset type
Gasturbinen mit nachgeschalteter Dampfturbine
Energy carrier
Erdgas
Location
Voerde (Niederrhein), Nordrhein-Westfalen
Registered operator
RWE Generation SE
Operating status
In Planung

A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE952338852908

New planned asset
Critical priority100

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

New planned 878.1 MW Gasturbinen mit nachgeschalteter Dampfturbine in Bergkamen, Nordrhein-Westfalen

Gasturbinen mit nachgeschalteter Dampfturbine

First observed
2026-09-11
Registered capacity
878.1 MW
Asset type
Gasturbinen mit nachgeschalteter Dampfturbine
Energy carrier
Erdgas
Location
Bergkamen, Nordrhein-Westfalen
Registered operator
Gaskraftwerk Bergkamen GmbH
Operating status
In Planung

A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE977698856878

New planned asset
Critical priority100

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

New planned 850.8 MW Gasturbinen mit nachgeschalteter Dampfturbine in Gundremmingen, Bayern

Gasturbinen mit nachgeschalteter Dampfturbine

Combined registered capacity across grouped units
979.85 MW
Registered units
29
First observed
2026-09-11
Registered capacity
850.8 MW
Asset type
Gasturbinen mit nachgeschalteter Dampfturbine
Energy carrier
Erdgas
Location
Gundremmingen, Bayern
Registered operator
RWE Generation SE
Operating status
In Planung

A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.

Source lineage

Presentation group: 29 registered MaStR units
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE968155469649, SEE965756082444, SEE977404654545, SEE922380340166, SEE971276194697, SEE900894444778, SEE921177994858, SEE914458821424, SEE983175903898, SEE965451885647, SEE966337374071, SEE976725563086, SEE916444687670, SEE945248948847, SEE996676429378, SEE947943737238, SEE929785881829, SEE906781049569, SEE939324670579, SEE926409412711, SEE983030959862, SEE905999571060, SEE996406323853, SEE979170976159, SEE988691126752, SEE935934259715, SEE907381622664, SEE905951934490, SEE966786659767

↑ Back to top

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.

Relevant Bundesländer (optional)
Relevant technologies (optional)

We'll only use this to follow up with a filtered weekly brief for your market. Read how your data is stored and how to withdraw at any time in our Privacy Policy.

New large assets (8)

New planned asset
Critical priority100

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

New planned 846 MW Gasturbinen mit nachgeschalteter Dampfturbine in Zolling, Bayern

Gasturbinen mit nachgeschalteter Dampfturbine

First observed
2026-09-11
Registered capacity
846 MW
Asset type
Gasturbinen mit nachgeschalteter Dampfturbine
Energy carrier
Erdgas
Location
Zolling, Bayern
Registered operator
Onyx Kraftwerk Zolling GmbH &Co. KGaA
Operating status
In Planung

A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE989789402819

New planned asset
Critical priority100

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

New planned 817.6 MW gas-generation asset in Schkopau, Sachsen-Anhalt

gas-generation asset

First observed
2026-09-11
Registered capacity
817.6 MW
Energy carrier
Erdgas
Location
Schkopau, Sachsen-Anhalt
Registered operator
GKS GmbH
Operating status
In Planung

A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE943675181523

New planned asset
Critical priority100

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Two new planned generation units in Gelsenkirchen, Nordrhein-Westfalen — 889.6 MW combined

Gasturbinen mit nachgeschalteter Dampfturbine

Combined registered capacity across grouped units
889.6 MW
Registered units
2
First observed
2026-09-11
Registered capacity
593.6 MW
Asset type
Gasturbinen mit nachgeschalteter Dampfturbine
Energy carrier
Erdgas
Location
Gelsenkirchen, Nordrhein-Westfalen
Registered operator
Uniper Kraftwerke GmbH
Operating status
In Planung

A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.

Source lineage

Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE930896060355, SEE985837541271

New planned asset
Critical priority100

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Two new planned generation units in Großkrotzenburg, Hessen — 887.2 MW combined

Gasturbinen mit nachgeschalteter Dampfturbine

Combined registered capacity across grouped units
887.2 MW
Registered units
2
First observed
2026-09-11
Registered capacity
592 MW
Asset type
Gasturbinen mit nachgeschalteter Dampfturbine
Energy carrier
Erdgas
Location
Großkrotzenburg, Hessen
Registered operator
Uniper Kraftwerke GmbH
Operating status
In Planung

A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.

Source lineage

Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE942562077253, SEE952825206252

New planned asset
Critical priority100

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Two new planned generation units in Karlsruhe, Baden-Württemberg — 875.8 MW combined

Gasturbinen mit Abhitzekessel

Combined registered capacity across grouped units
875.8 MW
Registered units
2
First observed
2026-09-11
Registered capacity
585.3 MW
Asset type
Gasturbinen mit Abhitzekessel
Energy carrier
Erdgas
Location
Karlsruhe, Baden-Württemberg
Registered operator
EnBW Energie Baden-Württemberg AG
Operating status
In Planung

A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.

Source lineage

Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE983841802050, SEE967019366087

New planned asset
Critical priority100

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Two new planned 560 MW units in Boxberg/O.L., Sachsen — 1.12 GW combined

Sonstige

Combined registered capacity across grouped units
1.12 GW
Registered units
2
First observed
2026-09-11
Registered capacity
560 MW
Asset type
Sonstige
Energy carrier
Erdgas
Location
Boxberg/O.L., Sachsen
Registered operator
Lausitz Energie Kraftwerke AG
Operating status
In Planung

A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.

Source lineage

Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE913385327436, SEE998894554863

New planned asset
Critical priority100

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Four new planned 560 MW units in Heinersbrück, Brandenburg — 2.24 GW combined

Sonstige

Combined registered capacity across grouped units
2.24 GW
Registered units
4
First observed
2026-09-11
Registered capacity
560 MW
Asset type
Sonstige
Energy carrier
Erdgas
Location
Heinersbrück, Brandenburg
Registered operator
Lausitz Energie Kraftwerke AG
Operating status
In Planung

A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.

Source lineage

Presentation group: 4 registered MaStR units
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE930140896327, SEE932992642459, SEE954455333353, SEE950406601014

New planned asset
Critical priority100

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Two new planned generation units in Werne, Nordrhein-Westfalen — 837.9 MW combined

Gasturbinen mit nachgeschalteter Dampfturbine

Combined registered capacity across grouped units
837.9 MW
Registered units
2
First observed
2026-09-11
Registered capacity
559.04 MW
Asset type
Gasturbinen mit nachgeschalteter Dampfturbine
Energy carrier
Erdgas
Location
Werne, Nordrhein-Westfalen
Registered operator
RWE Generation SE
Operating status
In Planung

A newly registered planned asset of this size may warrant early investigation for equipment, construction, grid or professional-services opportunities.

Source lineage

Presentation group: 2 registered MaStR units
Snapshot transition: First tracked snapshot → 11 Sept 2026
MaStR unit IDs: SEE998106364693, SEE914454617243

↑ Back to top

Timing changes (8)

Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 5 registered wind units in Wanderup, Schleswig-Holstein

Horizontalläufer

Registered units
5
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Wanderup, Schleswig-Holstein
Registered operator
Windpark Kieracker UG (haftungsbeschränkt) & Co. KG
Operating status
In Planung
Planned commissioning
Sept 2027 → Dec 2028
Change
+484 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 5 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE908700689801, SEE922923759974, SEE931873921669, SEE945040736536, SEE917466400421

Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 4 registered wind units in Cottbus, Brandenburg

Horizontalläufer

Registered units
4
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Cottbus, Brandenburg
Registered operator
LEWP Cottbus Ost GmbH & Co. KG
Operating status
In Planung
Planned commissioning
Nov 2027 → Aug 2028
Change
+262 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 4 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE942948643645, SEE987542532940, SEE937613613726, SEE917103359570

Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 2 registered wind units in Rabenau, Hessen

Horizontalläufer

Registered units
2
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Rabenau, Hessen
Registered operator
JUWI GmbH
Operating status
In Planung
Planned commissioning
Jul 2027 → Sept 2028
Change
+430 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 2 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE907274528790, SEE920775722245

Timing change
High priority65

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 4 registered wind units in Erkelenz, Nordrhein-Westfalen

Horizontalläufer

Registered units
4
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Erkelenz, Nordrhein-Westfalen
Registered operator
MLK Windpark Katzem Nr. 120 GmbH & Co. KG
Operating status
In Planung
Planned commissioning
Dec 2027 → Mar 2028
Change
+91 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 4 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE909649762150, SEE968050289519, SEE945969793870, SEE902855053067

Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 6.9 MW Horizontalläufer Ennigerloh, Nordrhein-Westfalen

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Ennigerloh, Nordrhein-Westfalen
Registered operator
BeBüWind GbR
Operating status
In Planung
Planned commissioning
Jun 2027 → Jan 2028
Change
+215 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE914845418510

Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 5.56 MW Horizontalläufer Rheda-Wiedenbrück, Nordrhein-Westfalen

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Rheda-Wiedenbrück, Nordrhein-Westfalen
Registered operator
Windrad Lintel II E 160 GmbH & Co. KG
Operating status
In Planung
Planned commissioning
Dec 2027 → May 2028
Change
+122 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE921675264750

Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 2 registered wind units in Kruft, Rheinland-Pfalz

Horizontalläufer

Registered units
2
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Kruft, Rheinland-Pfalz
Registered operator
ABO Energy Windpark 18 GmbH & Co. KG
Operating status
In Planung
Planned commissioning
Aug 2026 → Dec 2029
Change
+1241 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 2 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE905876661358, SEE959947585593

Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 6.8 MW Horizontalläufer Drahnsdorf, Brandenburg

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Drahnsdorf, Brandenburg
Registered operator
EE Schönerlinde GmbH & Co. KG
Operating status
In Planung
Planned commissioning
Aug 2026 → Nov 2029
Change
+1204 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE949294851786

↑ Back to top

Capacity changes (7)

Capacity change
Medium priority46

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered capacity reduced for 18.77 MW Kondensationsmaschine mit Entnahme Dinslaken, Nordrhein-Westfalen

Kondensationsmaschine mit Entnahme

Asset type
Kondensationsmaschine mit Entnahme
Energy carrier
Biomasse
Location
Dinslaken, Nordrhein-Westfalen
Registered operator
DHE Dinslakener Holz-Energiezentrum GmbH & Co. KG
Operating status
In Betrieb
Registered capacity
21.98 MW → 18.77 MW
Change
-3.2 MW

A material capacity reduction indicates a smaller registered asset capacity than in the previous snapshot.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE991539102320

Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 5 registered wind units in Wanderup, Schleswig-Holstein

Horizontalläufer

Registered units
5
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Wanderup, Schleswig-Holstein
Registered operator
Windpark Kieracker UG (haftungsbeschränkt) & Co. KG
Operating status
In Planung
Planned commissioning
Sept 2027 → Dec 2028
Change
+484 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 5 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE908700689801, SEE922923759974, SEE931873921669, SEE945040736536, SEE917466400421

Capacity change
Low priority41

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered capacity increased across 6 registered wind units in Hilchenbach, Nordrhein-Westfalen — 36 MW combined

Horizontalläufer

Combined registered capacity across grouped units
36 MW
Registered units
6
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Hilchenbach, Nordrhein-Westfalen
Registered operator
Alterric Deutschland GmbH
Operating status
In Planung
Registered capacity
3.5 MW → 6 MW
Change
+2.5 MW

A material capacity increase indicates a larger registered asset capacity than in the previous snapshot.

Source lineage

Presentation group: 6 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE924447498896, SEE987122644452, SEE938428285726, SEE947415655961, SEE912990489256, SEE981082008965

Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 4 registered wind units in Cottbus, Brandenburg

Horizontalläufer

Registered units
4
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Cottbus, Brandenburg
Registered operator
LEWP Cottbus Ost GmbH & Co. KG
Operating status
In Planung
Planned commissioning
Nov 2027 → Aug 2028
Change
+262 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 4 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE942948643645, SEE987542532940, SEE937613613726, SEE917103359570

Timing change
High priority68

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delayed for 2 registered wind units in Rabenau, Hessen

Horizontalläufer

Registered units
2
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Rabenau, Hessen
Registered operator
JUWI GmbH
Operating status
In Planung
Planned commissioning
Jul 2027 → Sept 2028
Change
+430 days

A later registered planned commissioning date may indicate asset delay or rescheduling.

Source lineage

Presentation group: 2 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE907274528790, SEE920775722245

Capacity change
Low priority40

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered capacity increased across 8 registered wind units in Franzenheim, Rheinland-Pfalz — 56 MW combined

Horizontalläufer

Combined registered capacity across grouped units
56 MW
Registered units
8
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Franzenheim, Rheinland-Pfalz
Registered operator
WPF Windpark Franzenheim GmbH
Operating status
In Planung
Registered capacity
5.56 MW → 7 MW
Change
+1.44 MW

A material capacity increase indicates a larger registered asset capacity than in the previous snapshot.

Source lineage

Presentation group: 8 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE987539984189, SEE987048648053, SEE940378993071, SEE914240720195, SEE995885995124, SEE969437719476, SEE947012849718, SEE984905462432

Capacity change
Low priority40

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered capacity increased for 7 MW Horizontalläufer Angermünde, Brandenburg

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Angermünde, Brandenburg
Registered operator
Windkraft Neukünkendorf GmbH & Co. KG
Operating status
In Planung
Registered capacity
5.7 MW → 7 MW
Change
+1.3 MW

A material capacity increase indicates a larger registered asset capacity than in the previous snapshot.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE951856471905

↑ Back to top

Operator changes (5)

Operator change
Low priority35

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered operator changed across 3 registered wind units in Möhnesee, Nordrhein-Westfalen

Horizontalläufer

Registered units
3
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Möhnesee, Nordrhein-Westfalen
Operating status
In Planung
Registered operator
Previous registered operator unavailable → Berlingsen Wind GmbH & Co. KG

A registered operator change may warrant investigation of the registered asset's current commercial context.

Source lineage

Presentation group: 3 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE914531865147, SEE926760641706, SEE923152875817

Operator change
Low priority35

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered operator changed across 2 registered wind units in Rehfelde, Brandenburg

Horizontalläufer

Registered units
2
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Rehfelde, Brandenburg
Operating status
In Planung
Registered operator
UKA Umweltgerechte Kraftanlagen GmbH & Co. KG → UGE Werder Eins GmbH & Co. KG Umweltgerechte Energie

A registered operator change may warrant investigation of the registered asset's current commercial context.

Source lineage

Presentation group: 2 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE970921485869, SEE930856107878

Operator change
Low priority35

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered operator changed across 4 registered wind units in Werningshausen, Thüringen

Horizontalläufer

Registered units
4
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Werningshausen, Thüringen
Operating status
In Planung
Registered operator
UKA Umweltgerechte Kraftanlagen GmbH & Co. KG → UGE Werningshausen GmbH & Co. KG Umweltgerechte Energie

A registered operator change may warrant investigation of the registered asset's current commercial context.

Source lineage

Presentation group: 4 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE924559861731, SEE908127526208, SEE981415392723, SEE968703508400

Operator change
Low priority35

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered operator changed across 13 registered wind units in Fehrbellin, Brandenburg

Horizontalläufer

Registered units
13
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Fehrbellin, Brandenburg
Operating status
In Planung
Registered operator
InVentus Energie GmbH → WP Manker-Protzen GmbH & Co.KG

A registered operator change may warrant investigation of the registered asset's current commercial context.

Source lineage

Presentation group: 13 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE901358413620, SEE981329693343, SEE998429014121, SEE947878098381, SEE964471948127, SEE932236169728, SEE920488326181, SEE954326397491, SEE980424428522, SEE977263890733, SEE924020772290, SEE978459842376, SEE941630809673

Operator change
Low priority35

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Registered operator changed for 6.8 MW Horizontalläufer Neuruppin, Brandenburg

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Neuruppin, Brandenburg
Operating status
In Planung
Registered operator
unlimited energy GmbH → WP Manker-Protzen SWN GmbH & Co. KG

A registered operator change may warrant investigation of the registered asset's current commercial context.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE933449299387

↑ Back to top

Commissioned assets (5)

Commissioned asset
Low priority27

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Asset commissioned: 2.67 MW Verbrennungsmotor Reken, Nordrhein-Westfalen

Verbrennungsmotor

Asset type
Verbrennungsmotor
Energy carrier
Biomasse
Location
Reken, Nordrhein-Westfalen
Registered operator
Benning Agrar-Energie GmbH
Operating status
In Betrieb
Lifecycle change
Planned → commissioned
Commissioning date
2026-07-01

The registered asset moved from a planned MaStR operating status to a non-planned status.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE913060333820

Commissioned asset
Low priority28

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

5 registered wind units commissioned in Bimöhlen, Schleswig-Holstein — 32.4 MW combined

Horizontalläufer

Combined registered capacity across grouped units
32.4 MW
Registered units
5
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Bimöhlen, Schleswig-Holstein
Registered operator
Windpark Bimöhlen GmbH & Co. KG
Operating status
In Betrieb
Lifecycle change
Planned → commissioned
Commissioning date
2026-07-28

The registered asset moved from a planned MaStR operating status to a non-planned status.

Source lineage

Presentation group: 5 registered MaStR units
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE957207568454, SEE959220888991, SEE955270649803, SEE915171284718, SEE962581958623

Commissioned asset
Low priority28

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Asset commissioned: 6.8 MW Horizontalläufer Ottenbüttel, Schleswig-Holstein

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Ottenbüttel, Schleswig-Holstein
Registered operator
Windpark Hohenaspe GmbH & Co. KG
Operating status
In Betrieb
Lifecycle change
Planned → commissioned
Commissioning date
2026-09-03

The registered asset moved from a planned MaStR operating status to a non-planned status.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE999733413310

Commissioned asset
Low priority28

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Asset commissioned: 6.8 MW Horizontalläufer Hohenaspe, Schleswig-Holstein

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Hohenaspe, Schleswig-Holstein
Registered operator
Windpark Hohenaspe GmbH & Co. KG
Operating status
In Betrieb
Lifecycle change
Planned → commissioned
Commissioning date
2026-09-03

The registered asset moved from a planned MaStR operating status to a non-planned status.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE920625007102

Commissioned asset
Low priority28

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Asset commissioned: 6 MW Horizontalläufer Syke, Niedersachsen

Horizontalläufer

Asset type
Horizontalläufer
Energy carrier
Wind
Location
Syke, Niedersachsen
Registered operator
6. SES Wind-Betriebs GmbH & Co. KG
Operating status
In Betrieb
Lifecycle change
Planned → commissioned
Commissioning date
2026-07-10

The registered asset moved from a planned MaStR operating status to a non-planned status.

Source lineage

Presentation group: 1 registered MaStR unit
Snapshot transition: 1 Jul 2026 → 11 Sept 2026
MaStR unit IDs: SEE982161063899

↑ Back to top

Receive a filtered weekly brief for your market

Tell us which Bundesländer and technologies you care about and we'll follow up with a weekly brief scoped to that — not the full report.