Timing change
High priority75

This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.

What this score is built from

  • Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
  • Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
  • Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.

Commissioning delay for 15 MW Horizontalläufer in Ausschließliche Wirtschaftszone

Ausschließliche Wirtschaftszone

Asset typeHorizontalläufer
Energy carrierWind
Registered operatorEnBW He Dreiht GmbH & Co. KG
A later registered planned commissioning date may indicate asset delay or rescheduling.
Combined registered capacity across grouped units
180 MW
Registered units
12
Asset type
Horizontalläufer
Energy carrier
Wind
Location
Ausschließliche Wirtschaftszone
Registered operator
EnBW He Dreiht GmbH & Co. KG
Operating status
In Planung
Planned commissioning
Jun 2026 → Oct 2026
Change
+93 days

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisConservative municipality/operator/category grouping
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.

1 Jul 2026 → 11 Sept 2026