Timing change
High priority68
This score estimates how much a registry change may be worth investigating — it is not a probability, a financial estimate, or a confirmed commercial opportunity.
What this score is built from
- Change type (18-35 pts): the kind of registry change — for example a new planned asset or a capacity increase — has a fixed base weight.
- Registered capacity (0-35 pts): larger registered MW earns more points, in tiers at 0 MW / 10 MW / 50 MW / 100 MW.
- Magnitude of change (0-30 pts): for changes with a measurable size — a capacity delta or a delay in days — a larger change earns more points, up to a cap.
Commissioning delayed for 2 registered wind units in Rabenau, Hessen
Rabenau, Hessen
Asset typeHorizontalläufer
Energy carrierWind
Registered operatorJUWI GmbH
Commercial interpretation
A later registered planned commissioning date may indicate asset delay or rescheduling.
Change summary
- Registered units
- 2
- Asset type
- Horizontalläufer
- Energy carrier
- Wind
- Location
- Rabenau, Hessen
- Registered operator
- JUWI GmbH
- Operating status
- In Planung
- Planned commissioning
- Jul 2027 → Sept 2028
- Change
- +430 days
Additional registered changes
These units also registered the change(s) below in this same update. They are shown for completeness and do not change the primary signal above.
Capacity change
- Registered capacity
- 5.53 MW → 7 MW (+1.47 MW / 27%)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (2)
SEE907274528790View official MaStR record ↗SEE920775722245View official MaStR record ↗
Grouping basis
Grouping basisConservative municipality/operator/category grouping
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
These registrations are grouped for presentation because they share location/operator/category characteristics. GridGraph does not assert that this grouping represents one canonical development project.
Snapshot transition
1 Jul 2026 → 11 Sept 2026