Schedule change
Opportunity · Low40

The opportunity score estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.

Opportunity score 40

  • Project scale (MW): 8
  • Event type: 4
  • Lifecycle stage: 10
  • Recency: 6
  • Operator identified: 10
  • Size of change: 2

Signal materiality 31

  • Event type: 16
  • Size of change: 8
  • MW affected: 7

Commissioning delayed by 29 days — 5.7 MW

Elsdorf, Nordrhein-Westfalen · Operator: Energiepark Elsdorf WP Frankeshoven GmbH & Co. KG

1 unit · 5.7 MW

MaStR evidence: HIGHExternal verification: Not checkedGrouping: Single unit
Asset typeHorizontalläufer
Energy carrierWind
Registered operatorEnergiepark Elsdorf WP Frankeshoven GmbH & Co. KG

The registered planned commissioning date moved by +29 days (01 Sept 2026 → 30 Sept 2026).

Why this ranks here. The registered operator is known. It affects only one 5.7 MW unit; short date shifts are common registry maintenance; no external evidence yet.

A short date shift is common and may be routine registry maintenance. Worth attention mainly if it is part of a wider pattern.
Developer servicesEngineeringMarket intelligence

Investigation hypotheses only. They are not evidence that any of these needs currently exist.

Planned commissioning
01 Sept 2026 → 30 Sept 2026 (+29 days)

GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.

Grouping basisSingle unit
A single MaStR registration.
Asset type (MaStR)
Horizontalläufer
Energy carrier (MaStR)
Wind
Operating status (MaStR)
In Planung

MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.

Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.

14 Sept 2026 → 16 Sept 2026

← Back to the brief · 2026-09-20