Opportunity · Low34
The opportunity score estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Opportunity score 34
- Project scale (MW): 9
- Event type: 6
- Lifecycle stage: 3
- Recency: 6
- Operator identified: 10
Signal materiality 19
- Event type: 12
- MW affected: 7
Wind unit commissioned — 7.2 MW — MaStR SEE948347059193
Bartow, Mecklenburg-Vorpommern · Operator: WB Energy Bartow 3 GmbH & Co. KG
1 unit · 7.2 MW
What changed
1 wind unit (7.2 MW) moved from planned to commissioned status in MaStR, with registered commissioning date 11 Sept 2026.
Why this ranks here. The registered operator is known. It affects only one 7.2 MW unit; already commissioned, so it is weighted below early-stage signals; no external evidence yet.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Operations, maintenance and technical management services
- Asset or company transaction advisory and technical due diligence
Verify next
- Confirm operating status and commissioning date in the official MaStR record
- Identify the operating company and public information on service arrangements
- Check for commissioning announcements
Change summary
- Registered capacity
- 7.2 MW
- Commissioning date
- 11 Sept 2026
- Lifecycle change
- Planned → commissioned
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (1)
SEE948347059193View official MaStR record ↗
Grouping basis
Stable MaStR location ID:
SEL902120953986A single MaStR registration.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Betrieb
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
14 Sept 2026 → 16 Sept 2026