Opportunity · High67
The opportunity score estimates how actionable a registry change may be as an investigation lead. It is not a probability, a financial estimate, or a confirmed commercial opportunity. How material the registry change itself is gets a separate signal materiality score.
Opportunity score 67
- Project scale (MW): 21
- Event type: 8
- Lifecycle stage: 10
- Recency: 6
- Operator identified: 10
- Multi-unit evidence: 9
- Size of change: 3
Signal materiality 59
- Event type: 16
- Size of change: 12
- MW affected: 16
- Units affected: 15
Commissioning delayed by up to 61 days — 11 units / 61.16 MW
Osterwieck, Sachsen-Anhalt · Operator: BürgerEnergiePark Druiberg GmbH & Co. KG
11 units · 61.16 MW
What changed
11 wind units registered a later planned commissioning date (+61 days).
Why this ranks high. Large 61.16 MW multi-unit signal, 11 registrations moving together and the registered operator is known.
Why it may matter
Possible relevance
Investigation hypotheses only. They are not evidence that any of these needs currently exist.
- Project development or development-management services
- Engineering and environmental services
Verify next
- Verify whether the date change reflects real rescheduling or a registry correction
- Check permitting and construction status
- Look for recent developer updates
Change summary
- Units with a new planned date
- 11
- Planned commissioning (same for every unit)
- Aug 2026 → Oct 2026 (+61 days)
Underlying registrations
GridGraph explains what changed here; each registration below links out to its own official MaStR record for independent verification. This is a group-level view — official links are unit-level evidence.
Underlying registrations (11)
SEE923194783002View official MaStR record ↗SEE965611938862View official MaStR record ↗SEE921734338453View official MaStR record ↗SEE942701385935View official MaStR record ↗SEE904699493788View official MaStR record ↗SEE961955578634View official MaStR record ↗SEE928400364181View official MaStR record ↗SEE908262824344View official MaStR record ↗SEE971876086033View official MaStR record ↗SEE972209952865View official MaStR record ↗SEE914107132826View official MaStR record ↗
Grouping basis
Supporting registry evidence: Identical registered capacity; Identical registered change on every unit; Same planned/commissioning date on every unit
These registrations share municipality, operator, technology and change type, and several registered facts agree. GridGraph groups them for presentation and does not assert that this is one canonical development project.
MaStR technical details
- Asset type (MaStR)
- Horizontalläufer
- Energy carrier (MaStR)
- Wind
- Operating status (MaStR)
- In Planung
Evidence confidence
MaStR evidence: HIGH. This describes how strongly MaStR supports the registry change itself. It does not mean the inferred commercial opportunity is real. External verification: not checked; no sources outside MaStR have been consulted.
Registry signal only. It does not establish procurement activity, construction status, contracts, financing or buyer intent.
Snapshot transition
14 Sept 2026 → 16 Sept 2026